/docs/guides/lab-assembly/msi-b850.md Added Optional RTE mounting section
Signed-off-by: Jakub Sobota <jakub.sobota@3mdeb.com>
This commit is contained in:
Binary file not shown.
|
After Width: | Height: | Size: 697 KiB |
@@ -92,6 +92,20 @@ Connect the RTE SPI header to the platform as described in the table:
|
||||
|
||||

|
||||
|
||||
## Optional: RTE Mounting and Cable Management
|
||||
|
||||
Where space and setup conditions allow, it is recommended to mount the RTE
|
||||
directly to the motherboard using nylon standoffs and screws, as shown in the
|
||||
picture below. This approach improves the overall stability of the test stand
|
||||
and reduces the risk of accidental disconnections during testing.
|
||||
|
||||

|
||||
|
||||
Additionally, it is advisable to secure the connection cables by routing and
|
||||
fastening them along the RTE board. Proper cable management minimizes strain
|
||||
on the connectors and helps prevent intermittent contact issues that could
|
||||
affect test reliability.
|
||||
|
||||
### Complete Setup
|
||||
|
||||
After preparing all of the connections also three activities should be
|
||||
|
||||